IT Park Phase 1
Area
50,000 sq.ft
Year
2023
Status
Completed
The Story Behind the Build
A landmark commercial development in Chennai's OMR technology corridor, this IT park was conceived as a next-generation workspace. The design prioritises collaborative environments, energy efficiency, and technological infrastructure that future-proofs the building for decades. With LEED Gold certification as a target from day one, the project pushed the boundaries of sustainable commercial construction in Tamil Nadu.
Client Requirement
The client, a leading SaaS infrastructure firm, needed a Grade-A office complex with LEED Gold certification, 500-seat capacity across 4 floors, a data centre, cafeteria, and scalable MEP infrastructure for future expansion.
Challenges Faced
Rocky terrain demanded controlled blasting and heavy-duty piling. Coordination of 15+ subcontractors across MEP trades while maintaining a fast-track 14-month schedule required real-time project management using BIM 360.
The Outcome
Achieved LEED Gold with 92/110 points. The building was fully leased within 60 days of completion, and the client has commissioned Phase 2 with an expanded scope. The project was awarded 'Best Commercial Project 2023' by the Chennai Builders Association.
Project Details
Project Gallery






Project Highlights
LEED Gold Certified
92/110 points — top-tier sustainability
Energy Efficient
30% below ASHRAE baseline energy use
Tier-3 Data Centre
Redundant power & cooling infrastructure
500+ Capacity
Flexible open-plan with breakout zones
Construction Timeline
Pre-Construction
Geotechnical survey, design development & permitting
8 WeeksSubstructure
Piled foundation, basement excavation & waterproofing
6 WeeksSuperstructure
Steel-concrete composite frame, curtain wall installation
16 WeeksMEP & Interiors
HVAC, fire safety, electrical & fit-out works
14 WeeksCommissioning
Systems testing, LEED documentation & occupancy permit
4 WeeksMaterials & Technology
"The Janalokaa team delivered a world-class tech park that stands shoulder to shoulder with any Tier-1 developer project. Their BIM-driven approach eliminated clashes and saved us significant time during MEP coordination."
Arun Prakash
CEO, NovaGrid Technologies